ACCA F5 - Performance Management
Deciding optimal production mix in situations with multiple
limiting factors:
Factors: For the case to exist production in functional or
divisional unit should pass through more than one factors (E.g. capital, labor,
machine1, machine2) out of which there should at least two limiting factors for
example ( i.e. machine1, and machine2)
or any other combination which limits production.
Objective function: Objective function simply maximizes
benefit (reduce cost / increase output / increase contribution / increase NPV
in case of investment appraisal) from total available units of decision
variables. Decision variables relate to goal/objective.
Constraints: All constraints are coded into linear inequalities
equations, which represent the sharing of know value of each available factor
in between decision variables. Constraints can take myriad of forms. They are: Typesof Constraints
Ø
Lower and upper bounds on the values of decision
variables. E.g x >= 10
Ø
Limitation constraints - relationship between
decision variables which does not exceed factor limit (2X + 3Y =< 500 hours)
Ø
Requirement constraints - relationship between
decision variables which should satisfy minimum set requirements (X + Y >=
50 units)
Ø
Ratio constraints - Relationship can be <=,
>=, or =, which compares value of two or more variables. (X / Y >= 2)
Ø
Balance Constraints - model process where
"inputs" must equal "outputs."
Graphical approach:
Ø
First straight line is traced in the graph,
which means the balanced constraints for each inequality.
Ø
Then, section represented inequality is
identified.
Ø
The process is repeated for all inequalities
Ø
This gives feasible reason
Ø
Finally, values of variables at intersections
are fed into objective function and best decision is made or objective function
isoline is drawn, projected and decision is made.
To maximise shareholders wealth and minimise the limitations
imposed by soft capital rationing, managers use this tool to decide on optimal mix
of projects which increase overall net present value (NPV) of combined
projects.
Excel solver is a tool available in Microsoft Excel to deal
problems related to limiting factors. Installation of Solver pack is essential
for using Excel 2007 to calculate decision variables.
Ø
Office button > Excel option > Add-Ins
> Excel Add-Ins > Go > Check - "Solver"
Then copy input values to excel sheet, go to Data
Ribbon > Analysis > Solver and
fill in the inputs required.
ACCA Article: Linear Programming
CIMA Article: Graphical Linear Programming
No comments:
Post a Comment